Start with a solved base case and a ranked list of critical contingencies.
Preferred action order
- Verify the contingency definitions, monitored elements, and limits.
- Group critical contingencies by common corridor, interface, or weak area.
- Apply preventive actions first: redispatch, shunts, tap changes, or topology changes that help multiple contingencies.
- Evaluate corrective actions next: post-contingency switching, redispatch, or RAS schemes with explicit triggers.
- Use load shedding only as a last-resort action and state that clearly.
- For recurring problems, recommend reinforcement or a revised operating guide.
Working rules
- Do not trust contingency results from a bad base case.
- Prefer actions that improve a family of contingencies rather than a single outage.
- Re-run the full monitored set after any candidate fix.
Deliver
- The critical contingencies and the shared weak pattern.