This skill handles SAP PP (Production Planning) including MRP, production orders, process orders, shop floor control, capacity planning, BOM management, routing, and PP-PI for process industries. Use when user mentions PP, MRP, MD01, MD04, production order, CO01, CO11N, MFBF, BOM, routing, work center, capacity, planned order, operation, confirmation, goods issue, backflush, MRP Live, MPS, demand management, scheduling, process order, PP-PI, KANBAN.
| Type | Description |
|---|---|
| PD | MRP — demand-driven (standard) |
| VB | Manual reorder point |
| VM | Automatic reorder point |
| ND | No MRP |
| MF | Make-to-order (individual requirements) |
| Key | Description |
|---|---|
| EX | Lot-for-lot (exact demand quantity) |
| FX | Fixed lot size |
| WB | Weekly lot size |
| MB | Monthly lot size |
| HB | Replenishment up to maximum stock level |
| Exception | Meaning | Action |
|---|---|---|
| 10 | Reschedule in | Move order earlier |
| 15 | Reschedule out | Push order later |
| 20 | Firm planned order — reschedule | Evaluate manually |
| 25 | Surplus | Cancel or reduce |
| 30 | New order required | Convert planned order |
CO01 (Create) → Release (CO02 / KOAB batch) → Goods Issue (MIGO 261)
→ Confirmation (CO11N) → Final Confirmation → TECO (technically complete)
→ Settlement (KO88) → CLSD (closed)
| T-code | Description |
|---|---|
| CO01 | Create production order |
| CO02 | Change production order |
| CO03 | Display production order |
| CO11N | Production order confirmation |
| CO13 | Cancel confirmation |
| CO24 | Missing parts list (component shortage) |
| COOIS | Production order information system |
| MIGO | Goods issue (261) / GR (101) for order |
Used in: chemical, pharmaceutical, food & beverage industries
| T-code | Description |
|---|---|
| COR1 | Create process order |
| COR2 | Change process order |
| COR6N | Process order confirmation |
| CORK | PI sheet (process instruction) execution |
| CORZ | Process order scheduling |
Process instructions (PI sheets): define what operators enter during production Master recipe (C201): replaces routing for process industries
| T-code | Description |
|---|---|
| CS01 | Create BOM |
| CS02 | Change BOM |
| CS03 | Display BOM |
| CS11 | BOM explosion (multi-level) |
| CS14 | BOM comparison |
| CS15 | Where-used list |
| Usage | Description |
|---|---|
| 1 | Production |
| 2 | Engineering / design |
| 3 | Universal |
| 5 | Sales |
| 6 | Costing |
Work Center (CR01 / CR02)
Routing (CA01 / CA03)
Reference Operation Sets (CA11)
| T-code | Description |
|---|---|
| CM01 | Capacity load overview (work center) |
| CM21 | Capacity leveling (interactive) |
| CM50 | Variable capacity planning |
| CM99 | Scheduling overview |
| Feature | ECC | S/4HANA |
|---|---|---|
| MRP run | MD01 | MD01N (MRP Live) recommended |
| MRP performance | Slower (sequential) | Parallel HANA-based |
| Exception handling | MD04 list | Enhanced exception management |
| Scheduling board | CM21 | Production Scheduling Board (Fiori) |
| Shop floor | COOIS | Manufacturing Execution Fiori apps |
| eWM integration | External WM | Embedded eWM (same system) |
| pMRP | Not available | Predictive MRP (AI-based exception detection) |