Skill for engineering change request and order processing through PLM systems
The Engineering Change Management skill provides capabilities for managing engineering changes through PLM systems, ensuring controlled modification of designs with proper impact assessment and approval workflow.
| Type |
|---|
| Description |
|---|
| Urgency |
|---|
| Approval Level |
|---|
| Class I | Form/fit/function change | Normal | Full review |
| Class II | Minor change, no F/F/F impact | Normal | Limited review |
| Deviation | Temporary non-conformance | Varies | Engineering |
| Waiver | Accept as-is before build | Varies | Engineering |
| Emergency | Safety/production critical | Urgent | Expedited |
1. Change Request (ECR)
- Problem/opportunity identification
- Preliminary impact assessment
- Initial approval to investigate
2. Change Investigation
- Detailed impact analysis
- Solution development
- Cost/schedule estimation
3. Change Order (ECO)
- Formal change documentation
- Approval routing
- Implementation planning
4. Implementation
- Document updates
- Manufacturing notification
- Effectivity management
5. Closure
- Verification of implementation
- Record completion
Required information:
- Problem statement
- Proposed solution (if known)
- Originator and date
- Affected items (preliminary)
- Impact assessment (preliminary)
- Priority/urgency
- Supporting documentation
| Category | Assessment Questions |
|---|---|
| Technical | Does it affect performance, reliability, safety? |
| Cost | What is development and recurring cost impact? |
| Schedule | What is timeline impact? |
| Manufacturing | Does it affect tooling, processes, suppliers? |
| Service | Does it affect spare parts, maintenance procedures? |
| Regulatory | Does it affect certifications, approvals? |
Required sections:
1. Change description
- What is changing
- Why change is needed
- How change will be implemented
2. Affected items list
- Part numbers
- Document numbers
- Revision levels (from/to)
3. Impact assessment
- By category (cost, schedule, technical)
- Risk assessment
4. Interchangeability
- Form/fit/function analysis
- Backward compatibility
5. Effectivity
- Serial number/date effectivity
- Retrofit requirements
6. Implementation plan
- Tasks and responsibilities
- Timeline
- Verification requirements
| Code | Meaning | Action |
|---|---|---|
| D | Direct interchangeable | Replace anywhere |
| O | One-way interchangeable | New replaces old only |
| N | Not interchangeable | Separate part number |
| R | Retrofittable | Can upgrade old units |
Form:
- Dimensions unchanged?
- Mounting unchanged?
- Interfaces unchanged?
Fit:
- Assembly process unchanged?
- Mating parts unaffected?
- Clearances maintained?
Function:
- Performance unchanged?
- Reliability maintained?
- Safety unaffected?
Typical approval levels:
1. Originator - Complete ECR/ECO
2. Design Engineering - Technical review
3. Analysis Engineering - Impact verification
4. Manufacturing Engineering - Process review
5. Quality Assurance - Compliance review
6. Program Management - Cost/schedule review
7. Configuration Management - Release authority
8. Customer (if required) - Acceptance
| Role | Focus Areas |
|---|---|
| Design Engineering | Technical correctness |
| Manufacturing | Producibility, tooling |
| Quality | Inspection, compliance |
| Supply Chain | Supplier impact, cost |
| Program Management | Schedule, budget |
| Customer | Contract compliance |
Serial number effectivity:
- Starting serial: S/N 100
- Ending serial: S/N 199 (or blank for ongoing)
Date effectivity:
- Effective date: 2026-02-01
Lot effectivity:
- Starting lot: LOT-2026-001
Implementation considerations:
- Work-in-process inventory
- Finished goods inventory
- Field units
- Spare parts inventory
- Documentation updates
- Training requirements
| Type | Update Required | Responsibility |
|---|---|---|
| Drawings | New revision | Design |
| Models | New revision | Design |
| Specifications | As needed | Engineering |
| Procedures | As needed | Manufacturing |
| Manuals | As needed | Publications |
| Training | As needed | Training |
{
"change_type": "ECR|ECO|deviation|waiver",
"problem_statement": "string",
"proposed_solution": "string",
"affected_items": [
{
"item_number": "string",
"current_revision": "string",
"item_type": "part|document|process"
}
],
"priority": "normal|urgent|emergency",
"originator": "string",
"supporting_documents": "array of references"
}
{
"change_document": {
"number": "string",
"type": "ECR|ECO",
"status": "draft|in_review|approved|implemented|closed"
},
"impact_assessment": {
"technical": "string",
"cost": "number",
"schedule": "string",
"manufacturing": "string"
},
"interchangeability": {
"code": "D|O|N|R",
"justification": "string"
},
"approval_routing": {
"current_step": "string",
"approvers": "array",
"target_completion": "date"
},
"implementation_plan": {
"tasks": "array",
"effectivity": "object",
"verification_method": "string"
}
}